ATSC´S Experience

SECRETARÍA DE LA CONTRALORÍA Y DESARROLLO ADMINISTRATIVO (SECODAM) TODAY SECRETARÍA DE LA FUNCIÓN PÚBLICA (SFP)/ CENTRO DE INVESTIGACIÓN EN CIENCIA APLICADA Y TECNOLOGÍA AVANZADA (CICATA-IPN).

Technical audit to the award process of International Public Biddings of PEMEX Refinación No. 18576042-021-98, 18576042-021-98, 18576042-022-98, 18576042-023-98, 18576042-037-98, 18576042-038-98, 18576042-039-98 and 18576042-040-98 for the Reconfiguration and Modernization of the Refineries “Francisco I. Madero” in Cd. Madero, Tams.; “Ing. Antonio M. Amor” in Salamanca, Gto. (2 turns); “Miguel Hidalgo” in Tula Hgo. (2 turns) and for the Project Consulting and Management contracts in the three mentioned Refineries and for the Cadereyta Refinery.

GOBIERNO DEL ESTADO DE TAMAULIPAS, GRUPO SERBO AND BUFETE INDUSTRIAL TWO DEVELOPMENT POLES OF THE PETROCHEMICAL INDUSTRY.

Feasibility Study (technical, financial and environmental) to the Executive Project of two development zones of the petrochemical industry located in the area of Coatzacoalcos, Ver., and in the area of Altamira, Tams.

SECRETARÍA DE LA CONTRALORÍA Y DESARROLLO ADMINISTRATIVO (SECODAM) TODAY SECRETARÍA DE LA FUNCIÓN PÚBLICA (SFP)/ CENTRO DE INVESTIGACIÓN EN CIENCIA APLICADA Y TECNOLOGÍA AVANZADA (CICATA-IPN).

Supervision / Technical “Operative” Audit for the review of the Reconfiguration and Modernization works of the Refinery “Ing. Héctor R. Lara Sosa” in Cadereyta de Jiménez, N.L. This Technical Audit included the construction of 10 new plants, the extension and modernization of 14 existing plants and the construction of a new 24” oil pipeline of 1280 Km between Nuevo Teapa, Ver. And the Cadereyta Refinery, and two 12” and 10” multi-purpose pipelines of 720 Km. The Technical Audit included engineering, procurement, construction, tests and commissioning of the various plants as well as the CAP contract. Investment of USD 1.600.000.000,00.

SECRETARÍA DE LA CONTRALORÍA Y DESARROLLO ADMINISTRATIVO (SECODAM) TODAY SECRETARÍA DE LA FUNCIÓN PÚBLICA (SFP)/ CENTRO DE INVESTIGACIÓN EN CIENCIA APLICADA Y TECNOLOGÍA AVANZADA (CICATA-IPN).

Supervision / Technical “Operative” Audit for the review of the Reconfiguration and Modernization works of the Refinery “Franciso I. Madreo” in Cd. Madero, Tamps. This Technical Audit included the construction of 16 new plants and the extension and modernization of 10 existing plants. The Technical Audit included engineering, procurement, construction, tests and commissioning of the various plants as well as the CAP contract. Investment of USD 1.200.000.000,00

SECRETARÍA DE LA CONTRALORÍA Y DESARROLLO ADMINISTRATIVO (SECODAM) TODAY SECRETARÍA DE LA FUNCIÓN PÚBLICA (SFP) / CENTRO DE INVESTIGACIÓN EN CIENCIA APLICADA Y TECNOLOGÍA AVANZADA (CICATA-IPN).

Supervision / Technical “Operative” Audit for the review of the engineering, procurement, construction, tests and commissioning termination works of the Retarded Coke Production Unit and Associated Gas Plant of 50,000 BPD. Investment of USD 250,000,000.00

PEMEX EXPLORACIÓN Y PRODUCCIÓN (PEP) Y CENTRO DE INVESTIGACIÓN EN CIENCIA APLICADA Y TECNOLOGÍA AVANZADA (CICATA-IPN).

Third party opinion about the analysis and resolution of 16 technical disputes between Pemex Exploración y Producción and the EPC contractor of 18 off-shore perforation platforms Akal-T-J in the Campeche Sound.

SECRETARÍA DE LA CONTRALORÍA Y DESARROLLO ADMINISTRATIVO (SECODAM) TODAY SECRETARÍA DE LA FUNCIÓN PÚBLICA (SFP) / CENTRO DE INVESTIGACIÓN EN CIENCIA APLICADA Y TECNOLOGÍA AVANZADA (CICATA-IPN).

Elaboration of "White Books" of 15 contracts celebrated between the Centro de Investigación en Ciencia Aplicada y Tecnología Avanzada with the Secretaria de la Controlaría y Desarrollo Administrativo and PEMEX Refinación and 1 contract with PEMEX Exploración y Producción.

AGREGADOS CONTROLADOS DE TABASCO, S.A. DE C.V.

Technical Financial Audit to the production, distribution, sales and administration processes of the company dedicated to the production of aggregates for concrete and surfacing for roads in two crushing plants in the State of Tabasco.

AUDITORIA SUPERIOR DE LA FEDERACIÓN (ASF).

Technical and Normative Audit to three public work contracts of Pemex Exploración y Producción in the Southern Region, which are:

  • Contract No. CORS-001/98, Optimization and Modernization of the Jujo Central Battery and Automation of the Jujo and Tecominoacan fields located in the Municipality of Huimanguillo, Tab.
  • Contract No. CORS-379/96, Construction of the 36” gas pipeline of 75 km at Cd. Pemex-Nuevo Pemex, Section I.
  • Contract No. CORS-389/96, Construction of the 36” gas pipeline of 75 km at Cd. Pemex-Nuevo Pemex, Section II.

GRUPO CRISOL, S.A. DE C.V..-BIENES INDUSTRIALES DE MÉXICO.

Technical Audit (Expert Opinion) to the (technical, financial and environmental) Feasibility Study and to the Executive Project for the relocation of its Polyester, Nylon, short fiber spinning plants as well as of their workshops and offices of its Industrial Complexes of Mexico City and Huejtzingo, Pue.

CORPORACIÓN DE INVESTIGACIÓN TECNOLÓGICA DE SANTIAGO DE CHILE.

Technical Audit (Expert Opinion) to the (technical, economical and environmental) feasibility study and executive project of an industrial complex for the recycling of PET material used for disposable bottles, their recovery and conservation as polyester flakes and filaments for plants of a capacity of 10, 20 and 30 tons / day.

FISOMEX, S.A. DE C.V.

Technical Audit (Expert Opinion) to the (technical, economical and environmental) feasibility study and executive project of the polyester plant located in Apizacpo, Tlax., to increase the production from 28.000 t/year to 58.000 t/year including two additional production lines and complementary auxiliary services.

SECRETARÍA DE SALUD

Technical and Normative Audit to the execution and supervision contracts of the termination of the Bodies I and IV of the National Rehabilitation Center of Mexico City. (2 construction contracts and 3 supervision contracts)

S. DE P. R. EL JAGUAR PALENQUE.

Supervision of the works of removal, uprooting, land leveling, preparation of meadows, construction of internal roads and boards as well as the facilities of the cattle breeding and fattening unit in the State of Chiapas.

CONTADURÍA MAYOR DE HACIENDA DE LA ASAMBLEA LEGISLATIVA DEL DISTRITO FEDERAL (CMHALDF) .

Technical, Normative and Operative Safety Audit for the construction and commissioning of Line “B” of the subway of Mexico City. The works included the Technical Audit of 25 construction contracts and 2 (foreign and local) supervisions, as well as the determination of the safety conditions under which the aforementioned Line “B” of the subway initiated and continued its operation.

INMOBILIARIA 3-I.

Technical Audit (Expert Opinion) of the (technical, economical and environmental) feasibility study and executive project for the development of a petrochemical industrial park property of Inmobiliaria 3-I, located south of the Morelos Complex in the State of Veracruz.

GRUPO CRISOL, S.A. DE C.V., ELECTRIC AND THERMIC COGENERATION.

Technical Audit (Expert Opinion) of the (technical, economical and environmental) feasibility study and executive project of the development of a cogeneration project with a capacity of 45 MW and 180 t/h of steam of 13 kg/cm2 in the Acrilia Industrial Complex in Cotaxtla, Ver. and transfer of electric power to its plants in Huejotzingo, Puebla and in Mexico City.

AUDITORÍA SUPERIOR DE LA FEDERACIÓN (ASF).

Technical, normative and operative audit to nine public work contracts of Pemex Exploración y Producción in the Southern Region, which are:

  • Contract PRSPPPPR-048/00DMX. Construction of three tanks with conical fix roof with membrane and a capacity of 100,000 barrels each, for gasoline storage at the sea terminal of Tuxpan, Ver.
  • Contract RSPMC-035/02BMX. Termination of construction of two sections of the new 24” oil pipeline Nuevo Teapa – Poza Rica – Cadereyta, sections I and III (from Km. 2+192 to Km. 116+655 and from Km. 95+739 to Km. 115+000 and hydrostatic test from Km. 0+000 to Km. 33+400 and from Km. 77+500 to Km. 120+732 (section I) and from Km. 82+800 to Km.116+160 (of section III).
  • Contract PMX-REF-OP-/03/02. Termination of construction of sections IV and V of the new 24” oil pipeline Nuevo Teapa – Poza Rica – Cadereyta (from Km. 114+122 to Km. 122+687 and from Km. 51+971 to Km. 60+979 and hydrostatic test from Km. 113+500 to Km. 122+687 and from Km. 34+300 to Km. 76+564.
    • Contract SD-TD-RG-005/01. Retrofit of the 30” oil pipeline Nuevo Teapa—Poza Rica section Mazumiapan – Poza Rica.
    • Contract PRSPR-050/99AMX. Gas-oil hydrosulphurization plant.
    • Contract PRSPR-050/99AMX. Naphta reforming plant U-901.
    • Contract PRSPR-050/99AMX. New Auxiliary Services Facilities .
    • Contract PRSPR-050/99AMX. Integration Works.
    • Contract PRSPR-050/99AMX. Extraordinary Unit Price Contract (Appendix 30)

S. DE P. R. EL JAGUAR PALENQUE.

Technical Audit (Expert Opinion) of the feasibility study for the Agro-industrial Complex CEPROBEX (Calf Production Center for Export), Palenque Chis.

LA VIRTUD, S de P. R. de R. L.

Technical Operative Audit of the feasibility study, basic engineering, detail engineering and project administration for the agro-industrial complex LA VIRTUD for the breeding, fattening and trading of livestock, TIF slaughterhouse, food plant in Chetumal, Q. Roo.

COMERCIALIZADORA COLOSSAL , S.A. DE C.V.

Feasibility Study, basic engineering, detail engineering and project management for the installation of a cold meat packing plant in Cancún, Q. Roo.

GOBIERNO DEL ESTADO DE QUINTANA ROO

Technical Audit to the Trust “Fondo de Garantía y Administración para la Construcción de un Centro de Producción y Comercialización Agroindustrial en Quintana Roo” Chetumal Q. Roo.

PROMOTORA Y EDIFICADORA MORELOS, S.A. DE C.V.

Construction of 850 housings in the development called “Texcali” located on the way to Nexquipayac No. 100, Municipality of Atenco, State of Mexico.

GRUPO PLEAMAR, S.A. DE C.V.

Planning, design and construction of a restaurant in the City of Cancún, Q. Roo.

PROMOTORA Y EDIFICADORA MORELOS, S.A. DE C.V. / SINDICATO NACIONAL DE TRABAJADORES ESPECIALIZADOS EN LA INDUSTRIA DE LA CONSTRUCCIÓN Y CONEXOS DE LA R.M., C.T.M.

Project Management in the construccion of 379 popular houses in Tepeji del Río, Hgo.

SECRETARÍA DE LA FUNCIÓN PÚBLICA / AEROPUERTOS Y SERVICIOS AUXILIARES (ASA).

Technical, normative and operative audit of Contract No. 091-04-OF02-10 Asphalt paving of runway, ground run, platform, ground run extension, construction of audiovisual elements and service road construction, Toluca (Toluca International Airport, State of Mexico).

Technical, normative and operative audit of Contract No. 231-04-NPF01-10. Ambulatory Extension second national reception area, second phase of ambulatory extension, National Area in the Terminal Building in the Mexico City National Airport .

Technical, normative and operative audit of Contract No. 060-04-NPF02-10. Construction of rainwater drainage along the roads in the current terminal and retrofit of sump 4, in the Mexico City Airport .

Technical, normative and operative audit of Contract No. 250-04-OF01-10. Parking lot for ASA and SENEAM Offices to be built in the group of General Airport and Auxiliary Service Offices ( Mexico , D.F.)

SECRETARÍA DE LA FUNCIÓN PÚBLICA / PEMEX PETROQUÍMICA (PPQ ).

Technical, Regulatory and Operative Audit of Contract No. CO-MO-016/2004 / AO-MO-008/2004. Modification of the storage system and in bulk loading in the current Polypropylene Plant in Petroquímica Morelos, S.A. de C.V. ( Coatzacoalcos , Ver.).

Technical, Regulatory and Operative Audit of Contract No. PP-OP-L-028/AP / 18572039-005-04. Integration and Service for the new Train “C” in the Polyethylene Plant “SWING”, New Train “C”, Complejo Petroquímico Morelos, S.A. de C.V. ( Coatzacoalcos , Ver.).

Technical, Regulatory and Operative Audit of Contract No. PP-OP-L-016/05P / 18572039-001-05. Development of Detail Engineering, procurement of construction equipment and materials, assays, training, startup preparations, startup and behavior tests for the storage and handling of polyethylene in the “Swing" Plant, and its convergence in Complejo Petroquímico Morelos, S.A. de C.V. (Coatzacoalcos, Ver.).

API DE TOPOLOBAMPO, S.A. DE C.V.

Design Consultancy Service and Implementation of the Initial Stages of the Management Model by means of the Balanced Scorecard Methodology in the API in Topolobampo , S.A.

DAIMLER CHRYSLER DE MÉXICO, S.A. DE C.V., / CONSTRUCCIONES BRAKOSA, S.A. DE C.V.

Arbitration due to differences in the construction of the Auto Shop and Product Engineering Laboratory in Mexico , D.F.

API DE PUERTO VALLARTA, S.A. DE C.V.

Design Consultancy Service and Implementation of the Initial Stages of the Management Model by means of the Balanced Scorecard Methodology in the APIVAL

HUTCHISON PORT HOLDINGS, S.A. de C.V.

Consultancy Services for the Technical and Legal Revision of Contractual Documents for the Turnkey Project for the Container Terminal in Lázaro Cárdenas , Mich.

SECRETARÍA DE LA FUNCIÓN PÚBLICA

Technical, normative and operative audit to public works by SECRETARÍA DE COMUNICACIONES Y TRANSPORTES (SCT).

Contract 1-4-CE3-A-567-W-01. Construction of earthworks, drainage works, asphalt concrete pavement, complementary works and signaling, along the Puebla – Xalapa Highway , Perote Bypass Span, Sub-span Km. 103+000 to Km. 111+581.40, in the State of Veracruz.

Contract 1-4-CE-A-586-W-0-1. Construction of earthworks, drainage works, asphalt concrete pavement, complementary works and signaling, along the Puebla – Xalapa Highway , Perote Bypass Span, Sub-span Km. 94+000 to Km. 103.000, in the State of Veracruz .

Contract 9-T-CB-A-532-W-0-9. Isolated reconstructions, by means of arbitration, scarification of the current pavement, being establishing with Portland cement, patching, hot asphalt mixture pavement, drainage works, signaling and diverse jobs (Goal 20.0 Isolated Km.) between Km. 39+000 and 186+000 (Goal 20 Isolated Km), on the Pinotepa Nacional – Pochutla Span, on the Pinotepa Nacional – Salina Cruz highway, State of Oaxaca .

Contract 0-T-CB-A-521-W-0-0. Emergent construction of a vehicular bridge, cased upon deep foundation and superstructure with pre-stressed elements, including its accesses, located at Km. 147+300 along the Ver./Oax. State Limit – Salina Cruz Span on the Coatzacoalcos – Salina Cruz Highway , in the State of Oaxaca .

Contract 1-T-CE-A-501-W-0-1. Construction of earthworks, drainage works, complementary works, induced works, marginal works, paving and signaling at Km. 8+000 to Km. 10+000, including the junction at the “Santa Lucía” level and the junction at the “Tule I” slope with its access earthworks, located at kilometers 10+036 and 510+040, on the Oaxaca – Mitla Span on the Oaxaca – Istmo de Tehuantepec Highway , in the State of Oaxaca .

Contract 1-T-CE-A-501-W-0-1. Periodic conservation by milling the current highway, patching, construction of a relevelling bed, construction pavement with asphalt concrete and geotextiles, from Km. 139+900 to 160+000 along the Ver./Oax. States – La Ventosa Span on the Coatzacoalcos – Salina Cruz Highway , in the State of Oaxaca .

Contract 3-T-CF-A-503-W-0.3. Pavement renewal, with type “D” specification at a 7 Km span, included in Km. 13+900, starting at San Miguel Talea de Castro, with a total length of 22.0 Km from the country lane Las Maravillas – San Miguel Talea de Castro, in the State of Oaxaca .

Contract 4-L-CE-A-579-W-0-4. Renewal construction of the Chilpancingo – Acapulco Highway , Chilpancingo – Petaquillas Span Km. 0+000 to Km. 3+1000, consisting of the construction of earthworks, drainage works, asphalt concrete pavement, complementary works and signaling in the State of Guerrero .

Contract 1-L-CE-A-570-W-0-1. Construction of earthworks, drainage works, four (4) level junctions, asphalt concrete pavement, complementary works, signaling and marginal works on the Ixtapa Bypass.

Contract 1-K-CB-A-507-W-0-1. Periodic conservation by recovery of pavement and sheet of nominal asphalt concrete from Km. 57+000 to Km. 61+000 and from Km. 71+000 to 87+000 on the Acámbaro – Salvatierra Span on the Morelia – Celaya Highway , in the State of Guanajuato .

COMISIÓN ESTATAL DEL AGUA DEL ESTADO DE BAJA CALIFORNIA / SECRETARÍA DE LA FUNCIÓN PÚBLICA / INSTITUTO MEXICANO DE AUDITORÍA TÉCNICA, A.C.

SOCIAL WITNESS in Bidding No. 32130001-001-06 to Lend services for the conduction and enlargement of the Río Colorado – Tijuana (ARCT) aqueduct, its operation and maintenance.

SECRETARÍA DE LA FUNCIÓN PÚBLICA

Technical, normative and operative audit to public works by PEMEX Gas y Petroquímica Básica.

Contract PG-OP-A-019/04P. Construction of Modular Cryogenic Plant 3, enlargement to the Distribution Terminal and Storage Area in the Burgos Gas Processing Center, in Reynosa, Tamaulipas.

Contract PGB-SD-GRM-0055/2005. Construction of the Compression Station, in the Emiliano Zapata Municipality in the State of Veracruz .

Contract PG-OP-A-006/05P. Construction of Modular Cryogenic Plant 4, in the Burgos Gas Processing Center, in Reynosa , Tamaulipas.

SECRETARIA DE DESARROLLO URBANO, OBRAS PÚBLICAS Y VIVIENDA, GOBIERNO DEL ESTADO DE YUCATÁN

Technical Audit, Technical Dictum and Cost Verification of the Construction of the Civil Works for the YUCATÁN PENINSULA SPECIALTY REGIONAL HOSPITAL . Includes the technical, regulatory and operative audit of 16 construction contracts.

SECRETARÍA DE LA FUNCIÓN PÚBLICA

Technical, normative and operative audit to public works by PEMEX Exploración y Producción.

Contract 4112558320. Cementation, stimulation and different pumping jobs in wells located within the jurisdiction of the Drilling and Maintenance Operative Units at the Reforma, PEMEX City , and Delta del Tonará wells, as well as others in the South Division, Drilling and Maintenance Management Wells, South Division, in Villahermosa , Tab.

Contract 4112558322. Cementation, stimulation and different pumping jobs in wells located within the jurisdiction of the Drilling and Maintenance Operative Units at the Reforma, PEMEX City , and Delta del Tonará wells, as well as others in the South Division, Drilling and Maintenance Management Wells, South Division, in Villahermosa , Tab.

Contract 4110058150. Jobs entailing chemical treatment, nitrogen pumping and induction in marine oil wells with a located support ship, which included laboratory, nitrogen and chemical product supply services required to dose the treatment fluids. Drilling Material Resource Assistant Office Villahermosa Headquarters, Tab., with the jobs located on territorial waters and in the economic zone of the Country.

Contract 4110058152. Jobs entailing chemical treatment, nitrogen pumping and induction in marine oil wells with a located support ship, which included laboratory, nitrogen and chemical product supply services required to dose the treatment fluids. Drilling Material Resource Assistant Office Villahermosa Headquarters, Tab., with the jobs located on territorial waters and in the economic zone of the Country.

Contract 4145058680. Construction of Pipelines in the Arcabuz, Arcos, Calabaza, Comitas, Cuitlahuac, Fundador and/or other Fields in the Burgos Integral Operative Center , Burgos Integral Operative Center contracts, Reynosa .

Contract 414504818. Construction and Enlargement of Collection Stations at the Canon, Galia, Sultán and/or other Fields in the Burgos Integral Operative Center , Tamaulipas and Nuevo León.

SECRETARÍA DE LA FUNCIÓN PÚBLICA

Technical, normative and operative audit to public works by PEMEX Gas Y Petroquímica Básica.

Contract PG-OP-A-042/05P. Conditioning and Repair Package of Sweet Humid Gas in the Burgos CPG, in Reynosa , Tamps.

Contract PG-OP-L-001/04P. Design, Equipment and Material Procurement, Construction, Infrastructure Equipment Installation, Startup Preparation, Training and Guarantee Test of a Sulfur Recovery Plant with Claus Type Process with one Thermal Stage and three Catalytic Stages, with a nominal processing capacity of 10 ton/day at the La Cangrejera CPQ , Ver.

SECRETARÍA DE LA FUNCIÓN PÚBLICA

Technical, normative and operative audit to public works by PEMEX Petroquímica.

Contract CO-MSI-019/05. Integral Maintenance, Inspection, Retrofit of Pipelines belonging to PEMEX Petroquímica (South and North Zones in the State of Veracruz, and South Zone in the State of Oaxaca).

Contract CO-MSI-017/05. Maintenance and Retrofit of the inter-complex Rack System at the following spans: Span 2; Bridge No. 1 from Pajaritos to Bridge IV Pajaritos (Old Rack); Span 3: Bridge No II Pajaritos to Bridge 6 Pajaritos (New Rack); Span 7: Bridge No. 11 Pajaritos to the Morelos property boundary; Span 8: Northern Outer Fence East Morelos Terminal to Dock No. 9; Span 10; Bridge No. 7 to smokeless Burners in Pajaritos (South Zone in the State of Veracruz ).

INSTITUTO NACIONAL DE MEDICINA GENÓMICA (INMEGEN).

Technical Accountable Dictum for two claims presented by INMEGEN contractors.

QUÍMICA FOLIAR, S.A. DE C.V.

Project Management, Basic Engineering, Detail Engineering for the construction of the WUXAL-1 line in Naucalpan, State of Mexico .

CORPORACIÓN GEO S.A DE C.V. (GEO HOUSES).

  • Revision and update of the corporative strategy.
  • BALANCED SCORECARD implementation as a strategy management model:
    • Design of the Corporative Strategic Map, Key Performance Indicators, Goals and Strategic Projects.
    • Definition and jump-start of a permanent follow-up mechanism for the strategy execution.

CABLES Y ESTAMPADOS S.A (CYESA). 

  • Diagnosis and recommendations regarding the follow-up method for corporative priorities.
  • Analysis and improvement proposal of:
    • Follow-up indicators of the operational and strategic performance.
    • Projects (selection method and follow-up model).

SECRETARÍA DE LA FUNCIÓN PÚBLICA

Technical, normative and operative audit to public works by Caminos y Puentes Federales de Ingresos y Servicios Conexos.

Contract No. 4500007916/07. Structural renovation of pavement from Km. 195+000 to 220+000. Includes horizontal and vertical signalization of C.D. Cuacnopalan - Oaxaca. (Oaxaca portion Management).

Contract No. 4500007685/07. Structural renovation of pavement from Km. 120+000 to Km. 155+000. Includes horizontal and vertical signalization of C.D. Cuacnopalan – Oaxaca. (Oaxaca portion Management).

SECRETARÍA DE LA FUNCIÓN PÚBLICA

Technical, normative and operative audit to public works by Comisión Nacional del Agua.

Contract No. SGIH-OCFS-CHS-07-021-FN-LP. Excavation of pilot course in the Suchiate river, at Adolfo Robles bridge in Cd. Hidalgo, along a portion of approximately 3 Km., in the Suchiate municipality, State of Chiapas (South Border Basin Organization, Los Laguitos, Tuxtla Gutiérrez, Chiapas)

Contract No. SGIH-OCFS-CHS-07-022-FN-LP. Excavation of pilot course in the Suchiate river, at Suchiate 2 bridge in Cd. Hidalgo, along a portion of approximately 3 Km., in the Suchiate municipality, State of Chiapas (South Border Basin Organization, Los Laguitos, Tuxtla Gutiérrez, Chiapas).

Contract No. SGIH-OCFS-CHS-07-121-FN-LP. Construction and elevation of protection rims on the right-hand bank of the Suchiate river, with rocking on wet slope and protection with flexible type 2 concrete carpet on dry slope, at Cd. Hidalgo in the Suchiate municipality, State of Chiapas (South Border Basin Organization, Los Laguitos, Tuxtla Gutiérrez, Chiapas).

AUTOSUR, S.A. DE C.V.

Study of alternate cities (Villahermosa, Tab., Mérida, Yuc. and Cancún, Q. Roo.), for the installation of corporate offices.

AUDITORÍA SUPERIOR DE LA FEDERACIÓN PÚBLICA

Technical, normative and operative audit to public works by PEMEX EXPLORACIÓN Y PRODUCCIÓN:

Contract 420836802. Procurement and construction of two oil and gas pipelines, 30”Ø, line 38 from detonation in line 1 towards submarine PLEM from the FPSO, one oil and gas pipeline, 30” Ø line 40 from 8 towards the FSPO, one gas pipeline, 24”Ø line 41 of submarine PLEM from the FPSO towards PP-ZAAP-C and submarine PLEM for the FPSO of KUMALOOB-ZAAP integral project in Sonda de Campeche, Gulf of México.

Contract PEP-O-IE-336/04. Engineering, procurement and construction of two living quarter platforms called HA-KU-S and HA-KU-M, with capacity for 220 people each; the scope includes pilings, substructure, superstructure, living quarters module, aluminum heliport and all systems necessary for its autonomous operation; testing in yard, loading, mooring and technical assistance during installation of the structures, interconnections, tests, and offshore startup in the Ku-Maloob-Zaap field, sonda de Campeche.

Contract 428236850. Construction of 24ӯ, by 5.5 Km. oil and gas pipeline from satellite platform ABK-B to permanent plataform ABK-A, and interconnections to existing facilities. Includes supply, protection, ballast, layout and hydrostatic tests.

SECRETARÍA DE LA FUNCIÓN PÚBLICA.

Technical, normative and operative audit to public works by PEMEX EXPLORACIÓN Y PRODUCCIÓN:

Contract 414044821. Hydraulic breakings with goosenecks in wells located in the Paleocene strip, or in any other in the Activo Burgos of the North Region, Cuenca Burgos y Sabinas (Unidad Operativa de Perforación, Reynosa, Tamps).

Contract 418235964. Construction of a module between platforms AKAL-C7 and AKAL-C8, to locate supplementary works including administrative offices, workshops, restrooms and warehouses. Gas processing center of AKAL-C complex (Residencia de Obras, SECSM, Cd. Madero, Tamps).

ARCOS SERCAL DE MÉXICO, S.A. DE C.V. (McDonald´s)

Consulting services in Strategic Planning.

INSTITUTO TECNÓLOGICO Y DE ESTUDIOS SUPERIORES DE MONTERREY, CAMPUS SANTA FE). (ITESM Campus Santa Fe).

Course on Strategic Planning and Balanced Scorecard.

TELESERVICIOS POPULARES, S.A. de C.V.

Integral management services.

 

 

©2005 ATSC, S.A. de C.V.